| ID | Task_Name | Duration | Start_Date | Finish_Date | Predecessors | Resource_Names |
| 1 | Submit proposal | 0 days | Fri 15/03/02 | Fri 15/03/02 | | Management |
| 2 | Decision on preferred bidders | 0 days | Mon 18/03/02 | Mon 18/03/02 | | The Society of C & P |
| 3 | Present propsal | 0 days | Fri 29/03/02 | Fri 29/03/02 | 2 | Management |
| 4 | Award contract | 0 days | Fri 29/03/02 | Fri 29/03/02 | 3 | The Society of C & P |
| 5 | Scope | 4 days | Mon 01/04/02 | Thu 04/04/02 | 4 | |
| 6 | Confirm project scope | 8 hrs | Mon 01/04/02 | Mon 01/04/02 | | Management |
| 7 | Define preliminary resources | 1 day | Tue 02/04/02 | Tue 02/04/02 | 6 | Project Manager |
| 8 | Secure initial resources | 2 days | Wed 03/04/02 | Thu 04/04/02 | 7 | Project Manager |
| 9 | Scope complete | 0 days | Thu 04/04/02 | Thu 04/04/02 | 8 | |
| 10 | Analysis/Software Requirements | 14.5 days | Fri 05/04/02 | Thu 25/04/02 | | |
| 11 | Review needs analysis | 2 days | Fri 05/04/02 | Mon 08/04/02 | 9 | Management |
| 12 | Draft preliminary software specifications | 6 days | Tue 09/04/02 | Tue 16/04/02 | 11 | Analyst |
| 13 | Confirm preliminary budget | 2 days | Wed 17/04/02 | Thu 18/04/02 | 12 | Project Manager |
| 14 | Review software specifications/budget with team | 4 hrs | Fri 19/04/02 | Fri 19/04/02 | 13 | Project Manager,Analyst |
| 15 | Incorporate feedback on software specifications | 1 day | Fri 19/04/02 | Mon 22/04/02 | 14 | Analyst |
| 16 | Develop delivery timeline | 1 day | Mon 22/04/02 | Tue 23/04/02 | 15 | Project Manager |
| 17 | Obtain approvals to proceed (concept, timeline, budget) | 1 day | Tue 23/04/02 | Wed 24/04/02 | 16 | Management,Project Manager |
| 18 | Secure required resources | 1 day | Wed 24/04/02 | Thu 25/04/02 | 17 | Project Manager |
| 19 | Analysis complete | 0 days | Thu 25/04/02 | Thu 25/04/02 | 18 | |
| 20 | Design | 17.5 days | Thu 25/04/02 | Mon 20/05/02 | | |
| 21 | Review preliminary software specifications & graphical design | 3 days | Thu 25/04/02 | Tue 30/04/02 | 19 | Analyst |
| 22 | Develop functional specifications | 7 days | Tue 30/04/02 | Thu 09/05/02 | 21 | Analyst |
| 23 | Develop prototype based on functional specifications | 4 days | Thu 09/05/02 | Wed 15/05/02 | 22 | Analyst |
| 24 | Review functional specifications | 2 days | Wed 15/05/02 | Fri 17/05/02 | 23 | Management |
| 25 | Incorporate feedback into functional specifications | 1 day | Fri 17/05/02 | Mon 20/05/02 | 24 | Management |
| 26 | Obtain approval to proceed | 4 hrs | Mon 20/05/02 | Mon 20/05/02 | 25 | Management,Project Manager |
| 27 | Design complete | 0 days | Mon 20/05/02 | Mon 20/05/02 | 26 | |
| 28 | Development | 38 days | Tue 21/05/02 | Thu 11/07/02 | | |
| 29 | Review functional specifications | 1 day | Tue 21/05/02 | Tue 21/05/02 | 27 | Developer |
| 30 | Identify modular/tiered design parameters | 1 day | Wed 22/05/02 | Wed 22/05/02 | 29 | Developer |
| 31 | Assign development staff | 1 day | Thu 23/05/02 | Thu 23/05/02 | 30 | Developer |
| 32 | Develop code | 35 days | Fri 24/05/02 | Thu 11/07/02 | 31 | Developer |
| 33 | Developer testing (primary debugging) | 15 days | Wed 05/06/02 | Wed 26/06/02 | 32FS-75% | Developer |
| 34 | Development complete | 0 days | Wed 26/06/02 | Wed 26/06/02 | 33 | |
| 35 | Testing | 53.75 days | Tue 21/05/02 | Fri 02/08/02 | | |
| 36 | Develop unit test plans using product specifications | 4 days | Tue 21/05/02 | Fri 24/05/02 | 27 | Testers |
| 37 | Develop integration test plans using product specifications | 4 days | Tue 21/05/02 | Fri 24/05/02 | 27 | Testers |
| 38 | Unit Testing | 15 days | Wed 26/06/02 | Wed 17/07/02 | | |
| 39 | Review modular code | 5 days | Wed 26/06/02 | Wed 03/07/02 | 36,34 | Testers |
| 40 | Test component modules to product specifications | 2 days | Wed 03/07/02 | Fri 05/07/02 | 34,39 | Testers |
| 41 | Identify anomalies to product specifications | 3 days | Fri 05/07/02 | Wed 10/07/02 | 40 | Testers |
| 42 | Modify code | 3 days | Wed 10/07/02 | Mon 15/07/02 | 41 | Testers |
| 43 | Re-test modified code | 2 days | Mon 15/07/02 | Wed 17/07/02 | 42 | Testers |
| 44 | Unit testing complete | 0 days | Wed 17/07/02 | Wed 17/07/02 | 43 | |
| 45 | Integration Testing | 12 days | Wed 17/07/02 | Fri 02/08/02 | | |
| 46 | Test module integration | 5 days | Wed 17/07/02 | Wed 24/07/02 | 44 | Testers |
| 47 | Identify anomalies to specifications | 2 days | Wed 24/07/02 | Fri 26/07/02 | 46 | Testers |
| 48 | Modify code | 3 days | Fri 26/07/02 | Wed 31/07/02 | 47 | Testers |
| 49 | Re-test modified code | 2 days | Wed 31/07/02 | Fri 02/08/02 | 48 | Testers |
| 50 | Integration testing complete | 0 days | Fri 02/08/02 | Fri 02/08/02 | 49 | |
| 51 | Training | 50.75 days | Tue 21/05/02 | Tue 30/07/02 | | |
| 52 | Develop training specifications for end users | 3 days | Tue 21/05/02 | Thu 23/05/02 | 27 | Trainers |
| 53 | Develop training specifications for helpdesk support staff | 3 days | Tue 21/05/02 | Thu 23/05/02 | 27 | Trainers |
| 54 | Identify training delivery methodology (computer based training, classroom, etc.) | 2 days | Tue 21/05/02 | Wed 22/05/02 | 27 | Trainers |
| 55 | Develop training materials | 3 wks | Wed 26/06/02 | Wed 17/07/02 | 52,34,53,54 | Trainers |
| 56 | Conduct training usability study | 4 days | Wed 17/07/02 | Tue 23/07/02 | 55 | Trainers |
| 57 | Finalize training materials | 3 days | Tue 23/07/02 | Fri 26/07/02 | 56 | Trainers |
| 58 | Develop training delivery mechanism | 2 days | Fri 26/07/02 | Tue 30/07/02 | 57 | Trainers |
| 59 | Training materials complete | 0 days | Tue 30/07/02 | Tue 30/07/02 | 58 | |
| 60 | Documentation | 40.5 days | Tue 21/05/02 | Tue 16/07/02 | | |
| 61 | Develop Help specification | 1 day | Tue 21/05/02 | Tue 21/05/02 | 27 | Technical Communicators |
| 62 | Develop Help system | 3 wks | Tue 18/06/02 | Tue 09/07/02 | 61,32FS-50% | Technical Communicators |
| 63 | Review Help documentation | 3 days | Tue 09/07/02 | Fri 12/07/02 | 62 | Technical Communicators |
| 64 | Incorporate Help documentation feedback | 2 days | Fri 12/07/02 | Tue 16/07/02 | 63 | Technical Communicators |
| 65 | Develop user manuals specifications | 2 days | Tue 21/05/02 | Wed 22/05/02 | 27 | Technical Communicators |
| 66 | Develop user manuals | 3 wks | Tue 18/06/02 | Tue 09/07/02 | 65,32FS-50% | Technical Communicators |
| 67 | Review all user documentation | 2 days | Tue 09/07/02 | Thu 11/07/02 | 66 | Technical Communicators |
| 68 | Incorporate user documentation feedback | 2 days | Thu 11/07/02 | Mon 15/07/02 | 67 | Technical Communicators |
| 69 | Documentation complete | 0 days | Tue 16/07/02 | Tue 16/07/02 | 68,64 | |
| 70 | Pilot | 78.25 days | Thu 25/04/02 | Tue 13/08/02 | | |
| 71 | Identify test group | 1 day | Thu 25/04/02 | Fri 26/04/02 | 19 | Project Manager |
| 72 | Develop software delivery mechanism | 1 day | Fri 26/04/02 | Mon 29/04/02 | 71 | |
| 73 | Install/deploy software | 1 day | Fri 02/08/02 | Mon 05/08/02 | 50,72,69,59 | Deployment Team |
| 74 | Obtain user feedback | 1 wk | Mon 05/08/02 | Mon 12/08/02 | 73 | Deployment Team |
| 75 | Evaluate testing information | 1 day | Mon 12/08/02 | Tue 13/08/02 | 74 | Deployment Team |
| 76 | Pilot complete | 0 days | Tue 13/08/02 | Tue 13/08/02 | 75 | |
| 77 | Deployment | 5 days | Tue 13/08/02 | Tue 20/08/02 | | |
| 78 | Determine final deployment strategy | 1 day | Tue 13/08/02 | Wed 14/08/02 | 76 | Deployment Team |
| 79 | Develop deployment methodology | 1 day | Wed 14/08/02 | Thu 15/08/02 | 78 | Deployment Team |
| 80 | Secure deployment resources | 1 day | Thu 15/08/02 | Fri 16/08/02 | 79 | Deployment Team |
| 81 | Train support staff | 1 day | Fri 16/08/02 | Mon 19/08/02 | 80 | Deployment Team |
| 82 | Deploy software | 1 day | Mon 19/08/02 | Tue 20/08/02 | 81 | Deployment Team |
| 83 | Deployment complete | 0 days | Tue 20/08/02 | Tue 20/08/02 | 82 | |
| 84 | Post Implementation Review | 3 days | Tue 20/08/02 | Fri 23/08/02 | | |
| 85 | Document lessons learned | 1 day | Tue 20/08/02 | Wed 21/08/02 | 83 | Project Manager |
| 86 | Distribute to team members | 1 day | Wed 21/08/02 | Thu 22/08/02 | 85 | Project Manager |
| 87 | Create software maintenance team | 1 day | Thu 22/08/02 | Fri 23/08/02 | 86 | Project Manager |
| 88 | Post implementation review complete | 0 days | Fri 23/08/02 | Fri 23/08/02 | 87 | |
| 89 | Software development template complete | 0 days | Fri 23/08/02 | Fri 23/08/02 | 88 | |